Installation & handover — illustrative project activity
AG ACTIVE PLAY™ / INSTALLATION & HANDOVER

From site to first serve.

Eight stages, responsibilities and inspection hold points.

Discuss this workstream ↗
ILLUSTRATIVE PROJECT SCENE · NOT A DOCUMENTED AG PROJECT
PLANNING RESOURCE

Use this guidance to prepare a project brief. The selected OEM, appointed engineer and relevant authorities must confirm the final system, documents and site requirements.

01 / Pre-start & survey
Illustrative 01 / Pre-start & survey activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Approved drawings, site data, services search, permits, RAMS and lifting plan.

Responsible
Project manager / appointed surveyor
Evidence
Survey records, approved documents
Hold point
Release setting-out and ground works
02 / Civil works
Illustrative 02 / Civil works activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Survey setting-out; engineered foundation, drainage and reinforcement with concrete testing.

Responsible
Civil contractor / engineer
Evidence
Inspection requests, material and concrete test reports
Hold point
Foundation acceptance by appointed engineer
03 / Delivery & inspection
Illustrative 03 / Delivery & inspection activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Check packing lists, traceability, coating condition, glass defects, hardware and dry storage.

Responsible
Site manager / QA
Evidence
Delivery notes and incoming-material inspection
Hold point
Accept components for installation
04 / Steel installation
Illustrative 04 / Steel installation activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Use approved erection sequence, temporary stability and anchor systems; verify geometry and connections.

Responsible
Qualified installer / engineer
Evidence
Inspection records and torque checks where specified
Hold point
Release framing for glazing
05 / Glazing
Illustrative 05 / Glazing activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Specialist lifting, OEM supports, isolators and fixings, damage and clearance inspection.

Responsible
Qualified glazing contractor
Evidence
Panel identification and glass inspection
Hold point
Accept complete enclosure
06 / Turf
Illustrative 06 / Turf activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Confirm substrate acceptance; join, install infill and verify surface according to named OEM system.

Responsible
Sports surfacing contractor
Evidence
Surface acceptance and product records
Hold point
Release playing surface
07 / Lighting & accessories
Illustrative 07 / Lighting & accessories activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Install luminaires, wiring and net/doors in accordance with approved design; test electrics and lighting.

Responsible
Licensed electrical installer / court installer
Evidence
Electrical test and photometric acceptance
Hold point
Electrical/sports commissioning
08 / Commission & hand over
Illustrative 08 / Commission & hand over activity for padel project planning
ILLUSTRATIVE ACTIVITY / NOT A DOCUMENTED AG PROJECT

Confirm court dimensions, safety, glass, turf, drainage, lighting and final documents.

Responsible
Project team / consultant
Evidence
As-builts, warranties, certificates and maintenance plan
Hold point
Client acceptance

The stage order is illustrative and must be reconciled with the named manufacturer assembly manual, engineering controls and local HSE requirements.

Technical reference downloads
FROM GUIDANCE TO A CLEAR BRIEF

What does your project need?

Share the location, court quantity, site dimensions and delivery scope. We’ll help organise the questions for supplier and project review.

Start a project enquiry ↗Return to the court collection →